A350 Westbury

Westbury Completed 1

A350 re-opened on evening of Thursday 3 October

With works progressing well the A350 road closure was lifted on the evening of Thursday 3 October. All the major reconstruction and surfacing has now taken place.The remaining works will continue under temporary traffic management measures such as stop and go until the work has been fully completed, we hope this will be during some point next week. 

Phase 1

Work Area 1 A - Between Frogmore Road and Edwards Street

Work Area 1 B - Between Edwards Street and Station Road (B3097)

Phase 2

Work Area 2 A - Between Station Road (B3097) and High Street

Work Area 2 B - Between High Street to approximately 40m before Bratton Road (B3098)

Phase 3

Work Area 3 A - Between approximately 40m before Bratton road (B3098) and Orchard Road

Work Area 3 B - Between Orchard Road and Leigh Road (A3098)

Programme of Works

Geo grid and a groundsurvey works will be undertaken during the night shifts.

Date
Location
Closure
Work
Monday 16 September
Phase 1
24 hours
Planing off existing surface
Tuesday 17 September

Phase 1

24 Hours
Planing existing surface and laying new surface
Wednesday 18 September

Phase 1

24 Hours

Planing existing surface and laying new surface

Thursday 19 September

Phase 1

24 Hours

Laying new surface
Friday 20 September

Phase 1

24 hours

Planing existing surface and laying new surface
Saturday 21 September

Phase 1

24 Hours

Laying new surface

Date
Location
Closure
Work
Sunday 22 September
Phase 2
24 hours       
Laying new surface
Monday 23 September
Phase 2
24 hours
Planing existing surface and laying new surface
Tuesday 24 September
Phase 2
24 hours
Planing existing surface and laying new surface
Wednesday 25 September
Phase 2
24 hours
Laying new surface around ironworks
Date
Location
Closure
Work
Thursday 26 September   
Phase 3
24 hours    
Planing existing surface and laying new surface
Friday 27 September
Phase 3
24 hours
Planing existing surface and laying new surface
Monday 30 September
Phase 3
24 hours
Laying new surface
Tuesday 1 October
Phase 3
24 hours
Planing existing surface and laying new surface
Wednesday 2 October
Phase 3
24 hours
Laying new surface
Thursday 3 October
Phase 3
24 hours
Installation of new road markings
Date
Location
Closure
Work
4 to 11 October
All Phases
No Closures. Stop and Go to be usedIronwork readjustment and installation of new lining where required

Buses through Westbury during the town centre road closures.

Whilst the roadworks are taking place, buses will run through Westbury as follows:

First "Discover" bus service D1 - (Bath - Trowbridge - Westbury - Warminster - Salisbury)

Buses on service D1 will run normally until 21 September. From 22 September until the roadworks finish, buses on this service will use Eden Vale Road instead of Haynes Road and Warminster Road.  Buses will not be able to call at the bus top near the police station on Station Road but temporary bus stops will be erected along Eden Vale Road instead.

FromeBus local bus service 45

Buses on Westbury local bus services 45A and 45B will run normally until 21 September. From 22 September until the roadworks finish, these bus services will be combined to run as one hourly route, departing from Westbury High Street at 0930, 1030, 1130, 1230, 1330, 1440, 1540 and 1630. For further details please contact Frome Minibuses on 01373 471474.

FromeBus service 47 (Westbury - Dilton Marsh - Frome)

Buses on service 47 are expected to run normally until 25 September.  From Thursday 26 September until the roadworks finish, buses on this route will not be able to call at Chalford or Warminster Road, so instead will run to/from the High Street along Eden Vale Road.

Faresaver bus service 87 (Trowbridge - Westbury - Devizes)

Buses to Devizes on bus service 87 are expected to run normally during most of the roadworks. However on Monday 23rd September, buses to Devizes will not be able to call at the High Street or at the bus stop near Westbury Cemetery and so if you wish to travel from Westbury Town Centre towards Devizes on this date, please wait at the bus stop opposite the Police Station on Station Road. Whilst Haynes Road is closed, passengers travelling from Devizes to Westbury Town Centre will be set down outside the Police Station instead of Haynes Road.

For further information about these temporary bus arrangements, please ring Wiltshire Council's Passenger Transport Unit on 01225 718080.