Delay to the completion of The Packway roadworks in Larkhill

During the past four weeks, a considerable amount of progress has been made constructing the new roundabout on The Packway.

Gas, water, electricity and communications utilities have been laid and embedded within the groundworks. The utilities will  provide services to housing and the new primary school, which now has foundations and the erection of the steel work has almost completed.

The Packway will re-open on Tuesday 17 October.

Fargo Road will remain CLOSED / BLOCKED OFF to all through vehicle traffic until The Packway reopens. This measure has been put in place in reaction to the safety concerns of the residents and that deliberately removing or ignoring these road closures is unsafe. Please use the A303 as your diversionary route until The Packway reopens in October 2017.

 

Last updated: 19 September 2017 | Last reviewed: 19 September 2017

Share this article

Latest Tweets

12 HOURS AGO

@MandyCasavant Hi, you can email fleet.services@wiltshire.gov.uk for more information. ^JE

24 Sep 2018 16:23

12 HOURS AGO

@SarahC1562 Hi, please DM your full address and I can look into this for you. ^JE

24 Sep 2018 16:20

12 HOURS AGO

We're hosting our 2018 EmployAbility Fair at County Hall, Trowbridge, from 10am 2pm on 2 October. The event support… https://t.co/Rgn6IDLjHI

24 Sep 2018 16:16

14 HOURS AGO

Our friendly canvassers are out visiting homes and encouraging those of you who have not yet responded to our house… https://t.co/7BzU6tYYFO

24 Sep 2018 14:37