19 September 2017

Delay to the completion of The Packway roadworks in Larkhill

During the past four weeks, a considerable amount of progress has been made constructing the new roundabout on The Packway.

Gas, water, electricity and communications utilities have been laid and embedded within the groundworks. The utilities will  provide services to housing and the new primary school, which now has foundations and the erection of the steel work has almost completed.

The Packway will re-open on Tuesday 17 October.

Fargo Road will remain CLOSED / BLOCKED OFF to all through vehicle traffic until The Packway reopens. This measure has been put in place in reaction to the safety concerns of the residents and that deliberately removing or ignoring these road closures is unsafe. Please use the A303 as your diversionary route until The Packway reopens in October 2017.

 

Last updated: 19 September 2017 | Last reviewed: 19 September 2017

Share this article

Latest Tweets

21 MINUTES AGO

Local people and organisations got together in #Salisbury last month to ensure the city is prepared should there be… https://t.co/pkIrSdx2wy

22 Nov 2017 10:30

14 HOURS AGO

Packed meting for talks on the Maltings redevelopment in #Salisbury this evening #ourday https://t.co/fUusczDgBT

21 Nov 2017 21:16

18 HOURS AGO

Our pest control officers started 13 new rats treatments today. We have already treated more than 1200 properties f… https://t.co/M5bbi4Fw9P

21 Nov 2017 17:04

18 HOURS AGO

Our pest control officers have treated a property with carpet moths today using professional insecticides. #OurDay https://t.co/70Bj9ZHZVF

21 Nov 2017 16:57