Tannery Bridge Report No. 17 : 6th July 2007

Top

Progress Report: Week 17 ending 6th July 2007

Summary of progress

  • At the request of Mouchel, a safety inspection of the temporary road and footway structures was undertaken by  Alun Griffiths’ specialist sub-contractor. There were no reported concerns but the loose (noisy) carriageway panels, identified during the inspection, will be tightened by Alun Griffths.
  • The working platform for the piling plant has been extended to accommodate the piling operations through spans 1 – 4 (see photograph 4 below).
  • Alun Griffths’ nominated piling sub-contractor established their piling equipment in Span 1, in readiness to start piling operations next week.
  • Alun Griffths commenced damming operations to Spans 9-11 which were delayed from the previous week because of additional piling operations

Notable Events

  • The heavy weekend rainfall breached the existing damming arrangements and flooded the site (see photograph 1 below). The flooding delayed site operations by approximately one day; a delay that will not affect the delivery of the overall project.

Weather

Generally mild with heavy showers.

Planned works for week ahead

  • The damming works to existing spans 9, 10 and 11 will continue.
  • Subject to the progress of the damming works (above), demolition of spans 9 to 11 will start together with the removal of the demolition debris.
  • Piling operations will commence on the eastern abutment (Span 1) progressing at approximately 2 piles per day.
  • Alun Griffths’ pre-casting  sub-contractor, will mobilise pre-casting operations at Downton Industrial Estate. The casting and associated concreting activities are due to start on the 16th July.
  • Implementation of Phase 1 of the diversionary scheme involving the “Headlands Junction” and associated diversionary routes (delayed works), will be undertaken by Ringway Infrastructure Services.

Meetings held

  • None

Proposed Meetings

  • Monthly Progress Meeting between Alun Griffiths, Mouchel and Wiltshire County Council - Wednesday 11th July.
  • Party Wall Meeting with Building Surveyor  – 11th July
  • Conservation meeting with Salisbury District Council - Thursday 12th July
  • Meeting with Mill owners - 11th July
  • Local Liaison Meeting – 19th July

Other programming items or issues

  • Dates of forthcoming road closures: to be confirmed

The flooded site conditions following the weend rain,

30th June-1st July

The exposed weed grille, Waterside Mill.

The exposed original timber piles to the old span 4.

The excavation to the piling base, eastern abutment, new span 1

Contact Details

By Post

Highway Improvements
Environmental Services
Wiltshire County Council
County Hall
Bythesea Road
Trowbridge
Wiltshire
BA14 8JN

By Email

bridges@wiltshire.gov.uk

By Telephone

01225 713000

By Fax

01225 713400

By Hand

This can be either County Hall or via the contact point in Salisbury Library

Opening Hours

Monday to Friday 9am - 5pm

  Back to top

Primary Navigation

Top


Customer Contact Centre
Email: Customer Care

Telephone : 01225 713000
Textphone : 01225 712500
View Out of hours numbers

Opening Hours:
Mon to Thurs - 8.30am - 5.20pm
Fri - 8.30am - 5.00pm

Website enquiries
Email: Customer Care

Wiltshire County Council
Bythesea Road
Trowbridge
Wiltshire
BA14 8JN