CGR Terms of Reference 2021-2022
Timetable
The Review will aim to be completed within 12 months of the date of commencement.
An indicative timetable for the Review is as listed below. This is subject to variation by the Committee as appropriate, within the overall prescribed time limit. In particular, the Committee may vary the timetable to take account of any additional consultations that it deems appropriate. The Director for Legal and Governance may also vary the timetable in consultation with the Chairman of the Committee at any time, if appropriate, to be reported to the Committee.
Stage | Action | Dates |
---|---|---|
Pre-review | Liaising with parish councils on suggested areas for consideration for review and receipt of initial submissions. | May-August 2021 |
Stage one | Commencement of CGR - Terms of Reference published. | September 2021 |
Stage one | Schemes uploaded to public portal for any initial comments, to be updated with any relevant additional information. To include any further schemes received which fall within the scope of the Review. | 22 September 2021 - 31 October 2021 |
Stage two | Consideration of submissions received in relation to proposed schemes. Local briefings and meetings as appropriate with unitary councillors and/or parish representatives | 1 November 2021 - 31 December 2021 |
Stage two | Pre-consultation surveying. | 15 November 2021 - 31 December 2021 |
Stage two | Draft Recommendations prepared. | January - February 2022 |
Stage three | Draft Recommendations consultation. | 8 February 2022 - 5 April 2022 (8 weeks) |
Stage four | Consideration of submissions received. Final Recommendations prepared. | April/May 2022 |