Toggle menu

B4069 Lyneham Banks

Lyneham Banks landslip information and ongoing updates

The B4069 at Lyneham Banks has been closed since February 2022, when a major landslip broke up the road, moving it 25 metres downhill. Since then, the council has been working hard to establish the cause of the landslip and assess the best way to rebuild the road and prevent the landslip reoccurring.

The process began with months of careful assessment and detailed ground investigations, including drilling 31 boreholes and 21 trial pits, as well as extensive sampling and monitoring of water levels and ground movement to establish the cause and extent of the landslip. Analysis revealed that the landslip was probably triggered by a combination of factors, including historic weaknesses, increased groundwater flows, and additional loading due to nearby development.

Construction work has now started on site. The construction will include the installation of a piled retaining wall with associated ground anchors. A series of drainage systems will also be installed in the area to help manage groundwater flows.

December 2024 update

Works are progressing well on site, with all of the vertical and micro piling now complete. The piles will now be tied into a new capping beam which will hold the new structure together. The completion of the capping beam will be a major milestone in construction.

Alongside works to the main highway, we have also been regrading the upper and lower slopes either side of the road, in anticipation for the new land drainage installations. Further carriageway drainage has been installed to the west of the site. This will serve as a key connection and vital drainage of the site moving forward. The counterforts on the upper slope will start when the drainage on the south of the new road is completed to prevent accumulation of water on the new road from the upper slope.

As works progress on the main landslip, we are continuing to see movements further along the B4069 to the west. These movements have been monitored over a number of months and we have now developed a design to begin repairs, working with the construction team on site. We hope that these repairs will be able to be included within the current construction programme, however this will be subject to the level of movement and level of intervention required to safely re-open the road.

For the B4069 Lyneham Banks Project, we are committed to delivering initiatives that create a positive, lasting legacy for the area. By engaging with local residents and organisations, we aim to not only enhance the community's understanding of our work but also leave a meaningful impact that goes beyond the project itself. 

This month, working with main contractor Octavius we have focussed on showcasing career opportunities in the industry and inspiring the next generation of talent. We participated in the Wiltshire Council Highways and Transport Careers Fair and the Seetec Pluss Job Fair in Swindon, where our team connected with over 200 attendees across both events. These events allowed project managers, lead planners, public liaison manager, and quantity surveyors to share insights into their roles and the rewarding careers available within the civil engineering industry. We are also delighted to welcome two civil engineering students from Wiltshire College, who will join our team from November to December for hands-on placements, further strengthening our commitment to skills development and community growth through the B4069 Lyneham Banks Project. 

Lyneham Banks progress December 2024
Lyneham Banks progress December 2024
Lyneham Banks progress December 2024

Meet the contractor event 

In July we hosted a meet the contractor event at Bradenstoke Village Hall. We were really pleased to meet many of the residents and had a good attendance of more than 100 people stopping by to learn more about the project. Hosting the evening there was representation from both Octavius and Wiltshire Council, with questions about the project and other local works being answered.

Planning

In February 2024 a planning application was submitted with the proposals for the road. The planning application PL/2024/02330 can be viewed through Wiltshire Councils Planning Portal.

You can receive updates about Lyneham Banks by signing up to the Wiltshire Council newsletter (opens new window), and ticking the box for Lyneham Banks.

Investigations

Whilst movements on the main landslip have slowed considerably, we are still noticing movements further along the B4069 to the west.

We have been undertaking further surveys to help understand those wider and more progressive movements further along the B4069 and explore solutions. Observations have included an extended drone survey which has covered the entire B4069 from the current landslip down to the Clack Hill junction.

We are also undertaking weekly monitoring visits to record and track the current movements and more detailed inclinometer readings at monthly intervals.

Anticipated Programme (Subject to land agreements and planning)
StageTimescale
Design WorkComplete
Procurement Complete
PlanningComplete
ConstructionSummer 2024 - Spring 2025

Webinar - progress of the scheme

On Monday 24 April 2023, we held a webinar about the progress of the scheme to repair the B4069 Lyneham Banks, you can watch a recording of this via the link below. Also available, for download, are the webinar presentation, and a document capturing the questions and answers from the session (also listed in the frequently asked questions section below).

Watch a recording of the webinar (opens new window)

Lyneham Banks Webinar Presentation (OpenDocument text format, 6 MB)(opens new window)

Lyneham Banks webinar Q&A (OpenDocument text format, 440 KB)(opens new window)

Frequently asked questions

Share this page

Share on Facebook Share on Twitter Share by email